GAD-SL-009 | Helper 2 Duties |
Helper 2
1. 1. Prepare Next Coil to Run
2.
Pull Coils in Saddle
Closer to Recoiler
3.
Get Tag Off Next Coil
to Run & Take to Operator
4.
Roll Up Band
5.
Collapse Uncoiler
6.
½ (Jointly with Set-Up
Man): Remove Wood
7.
Push Off Tail of Coil
8.
Lower Buggy & Load Next
Coil
9.
Measure & Align Coil
10.
Lower Over Arm
11.
Cut Band Off Loaded Coil
12.
Spin Coil – Lap Facing Machine
13.
Recoiler: Move Car Under Coil & Set to Coil
14.
Lower Coil Car Over Arm
15.
Move Car Clear of Recoiler
16.
Change Tension Stand Arm
17.
Change Over Arm
18.
½ (Jointly with Set-Up Man): Dump or
Tie Scrap
19.
Align Steel with Separators
20.
Put Pads in Tension Stand
21.
Center Over Arm
22.
Build Tension Stand Arm
23.
Go to Uncoiler
Revision History
Revision Date | Revision Level | Changes Made |
09/29/09 | 0 | Original Version |