LYN-LRB-001  Redbud Procedure

Redbud Procedure

 

1.     Print out of pick list or Redbud schedule to be used to stage coils in order of use. If lineup is changed, Production Planner or Plant Manager will notify SRB Operator and correct schedule.

 

2.  Skid list is created per schedule and given to appropriate personnel.

 

3.     Using W/O's "Order spec" sections to determine sizes and leveler settings that will be input into SRB.

 

4.     Coil loaded onto SRB by appropriate personnel, tag is given to operator to verfiy correct coil is fed up per W/O.

 

 

5.     If slitting and leveling, Operator checks knife clearance.  If clearance is good, material is fed through the knives.  If clearance is incorrect, necessary adjustments are made.

 

           Frequency of Quality Measurements (BURR, WIDTH, CAMBER, FLATNESS, LENGTH, SQUARE) Record on LYN-F-001 (Cut to Length QA Form)

Tolerance Type Minimum Inspection Frequency
Stainless Steel & Aluminum CHECK SAMPLE PRIOR TO PUTTING LINE IN RUN + CHECK PIECE ONCE LINE RUN IS ESTABLISHED + LAST PIECE OF 1ST BUNDLE + LAST PIECE OF SKID AFTER EVERY 2,500 LBS + LAST PIECE OF RUN
TIGHT TOLERANCE
+/- 0.062" or tighter for LENGTH, WIDTH, or SQUARE
1/8" or less for FLATNESS
CHECK SAMPLE PRIOR TO PUTTING LINE IN RUN + CHECK PIECE ONCE LINE RUN IS ESTABLISHED + LAST PIECE OF 1ST BUNDLE + LAST PIECE OF SKID AFTER EVERY 7,000 LBS + LAST PIECE OF RUN
STOCK TOLERANCE Greater than +/- 0.062" for LENGTH, WIDTH, or SQUARE
Greater than 1/8" for FLATNESS
CHECK PIECE ONCE LINE RUN IS ESTABLISHED + LAST PIECE OF 1ST BUNDLE + LAST PIECE OF SKID AFTER EVERY 14,000 LBS + LAST PIECE OF RUN

 

 6.     Operator manually checks gauge (edge-crown-edge) on first and last bundle and near middle of the run.  Record on LYN-F-001.

 

      7.            If work order/part spec says "Residual Stress Check"; then check residual stresses per SMT-SH-001.

 

 

8.   Visual inspection for BURR, WIDTH, CAMBER, FLATNESS, LENGTH, SURFACE QUALITY, SHAPE Performed on every bundle, not recorded.

 

9. Width of master coil, at entry side of knives checked per Inspection Checkpoints 8.3.3.

10. If any check does not meet the Customer Part Specification/Job Requirements, QA is notified and will contact sales.

 

11.Sales to contact customer for deviation. If customer accepts deviation, thenn JDM100 (Deviation Request Form) will be filled out and signed (email or verbal acceptance is acceptable and should be documented by sales) and OK is noted on FOP 081 and/or work order. If customer does not accept deviation, the Production Planner is notified so replacement can be made and material is placed in reject warehouse for MRB disposition.

 

12. At packaging, appropriate personnel will write tag number on bundle to be visible where tag is hung.

 

 

 

Revision Historyy

Revision Date Revision Level Changes Made
11/8/16 1 Added Step 12
05/31/16 0 Original Version