UNCONTROLLED COPY
UNCONTROLLED COPY
SMT-QA-001 SMT Rev-Up Procedure

Sumter Rev-Up Procedure

 

 

1. The purpose of this procedure is to ensure that a customer notification of change to a print/drawing/or material specification (rev-up) is fully implemented throughout Jemison Metals.

 

2. When sales receives notification of a revision change, they should immediately send the revision change details to the Sumter Rev-Up email group. smtrev-up@jemisonmetals.com

 

3. Quality will then track the status of each step of the rev-up process utilizing the SMT Rev-Up Check Sheet JDM-F-011).

 

4. Upon completion of the checksheet steps, QA keeps the record on file according to the master list requirements.

 

 

 

 

 

Revision Date Revision Level Changes Made
12/27/17 0 Original Version