Sumter

Location Document Revision Date Revision Level Approval Authority Form Info
  Operating Procedures        
Receiving SMT-RC-001 Receiving Procedure 9/21/15 0 R. Richards  
Slitter SMT-SL-001 Slitter Procedure 03/07/13 1 R. Richards  
Slitter SMT-SL-002 Slitter Re-Spin Procedure 02/07/13 0 R. Richards  
Redbud SMT-SRB-001 Redbud Procedure 11/8/16 5 R. Richards  
Cut to Length SMT-CTL-001 Cut to Length Procedure 11/8/16 4 R. Richards  
CTL & Redbud SMT-SH-001 Residual Stress Check Procedure 10/26/11 0 R. Richards  
Shear SMT-SH-002 Shear Procedure 04/21/15 0 R. Richards  
All JM-OP-001 Tagging Procedure 04/21/15 0 R. Richards  
QA SMT-QA-001 SMT Rev-Up Procedure 12/27/17 0 R. Rowland
           
  Forms        
Receiving MF032 Incoming Inspection 06/22/11 7 R. Richards 6
Receiving FMA024 Receiving Checkoff 8/30/18 1 R. Richards 5
Production JDM-F-013 Weekly Mic Checksheet 08/31/18 0 R. Rowland 1
Slitter FOP015 Slitting Inspection (On Server) 02/16/01 1 R. Richards 2
Slitter FMA027 Slitter Calibration Checkoff 8/30/18 1 R. Richards 5
Sllitter FMA044 GE Coil Checklist 05/21/14 1 R. Richards 7
Slitter FMA045 GE Sheet Checklist 5/23/14 0 R. Richards 2
Redbud FMA 030 Redbud Maintenance Checkoff 8/30/18 1 R. Richards 5
Packline FMA 023 Packline Maintenance Checkoff 8/30/18 1 R. Richards 5
Packaging FMA 028 Woodpile Maintenance Checkoff 8/30/18 1 R.Richards 5
Slit Packline FOP076 Packing Tally Report 02/16/01 0 R. Richards 7
Cutline/Shear FOP081 Cutline/Shear Inspection (On Server) 02/16/01 1 R. Richards 2
Cutline FMA020 Cutline Calibration Checkoff 8/30/18 1 R. Richards 5
Shipping FMA026 Shipping Checkoff 8/30/18 1 R. Richards 5
Leveler JDM5 Packaging Checklist & Final Inspection Record 07/21/11 4 R. Richards 7
Training OJT6.2.4 Group Training 10/19/16 5 T. Bradt 4
Training JDM-F-030 SMT Slitter Operator Training Matrix 10/26/15 0 R. Richards 8
Training JDM-F-031 SMT Slitter Helper Training Matrix 10/26/15 0 R. Richards 8
Quality FQA029 Rockwell Check 8/30/18 1 R. Rowland 5
Quality Form 4.1-1 Document Change Request/Notice 1/2/20 3 R. Rowland 2
Quality JDM 100 Deviation Request Form 12/15/12 4 R. Rowland 2
Quality JDM-F-005 Trial Report 07/21/18 1 R. Rowland 2
Quality JDM-F-009 Nordfab Blank Inspection 04/30/24 3 R. Rowland 2
Quality JDM 501 Process Audit Checklist 11/8/16 1 R. Rowland 4
Quality JDM-F-011 SMT Rev-Up Checksheet 12/27/17 0 R. Rowland 2
Quality JDM-F-200 Process Change Form 8/30/18 R. Rowland 2
           
  Visual Aids        
All JDM-VA-001 JD Skid Types 08/31/10 0 R. Rowland  
Slitter JDM-VA-002 Slitter Process Flow 09/02/11 0 R. Rowland  
Cut to Length JDM-VA-003 Cut to Length Process Flow 09/02/11 0 R. Rowland  
Redbud JDM-VA-004 Redbud Process Flow 09/02/11 0 R. Rowland  
Redbud SMT-VA-005 BSH Skid Orientation 8/28/17 3 R. Rowland  
           
  Other        
Slitter SMT-CP001-Slitter Control Plan 09/02/11 0 R. Rowland  
Redbud SMT-CP002-Redbud Control Plan 09/02/11 0 R. Rowland  
Cut to Length SMT-CP003-CTL Control Plan 04/19/24 1 R. Rowland  
Slitter FM003-Slitter PFMEA 09/02/11 0 R.Rowland  
Redbud FM002-Redbud PFMEA 09/02/11 0 R. Rowland  
Cut to Length FM001-CTL PFMEA 04/19/24 3 R. Rowland  
           
  Forms Retention Legend        
  1 - QA Office 1 Year        
  2 - QA Office 2 Years        
  3 - Server 1 Year        
  4 - Server 2 Years        
  5 - Server 1 Month        
  6 - Receiving 1 Day        
  7 - Opns Mgr 2 Years        
  8 - HR 3 Years        
  9 - QA Indefinite        
           
  Back to Quality Intranet Home